Week of 6/10/19 - 6/15/19 

  • Trees under the Bloomer Mill Bridge were removed to prepare for rip-rap placement.
  • Guard posts on Boma Rd were painted.
  • Ditching on Birchwood Ave was finished.
  • Culverts in the Brookwood Addition were done.
  • On Cherrywood Drive, tree stumps were grinded.
  • Town of Shelby's Parks were mowed, trimmed and sprayed. Trees in the park were mulched.

 

Week of 6/3/19 - 6/8/19 

  • On Cherrywood Dr.  trees were removed.
  • Town of Shelby Ball Fields and Parks were mowed, trimmed. Trees in the park were mulched.
  • Mathy Construction finished the last lift on Wedgewood East and Hickory Ln.
  • The guardrail on Boma Rd was repaired.
  • Birchwood Ave was ditched.
  • Our 3rd Large Item Drop - Off on Saturday June 8th, 2019, was completed.